Power Distribution Setup / 电源分配安装

⚡ Power Team / 电源组

Coordinator / 协调人: JP Bourgeois 柏松

Team / 小组 Members / 成员
Power Distribution / 电源分配 • Han 韩丞华 🔑
•

🇬🇧 English Instructions

Purpose
Distribute power to all A/V equipment and the stage, ensuring safe cable routing and connections according to the schematics.

⚠️ Safety & Installation Notes
• USE QUALIFIED ELECTRICIAN to connect PDU to venue distribution board (3-phase supply) in corridor behind stage.
• Do not overload electrical circuits.
• Ensure that pedestrians are protected from trip hazards and electric shock. Use cable covers or suspend wiring overhead.

Required References

Required Equipment Cases

  • PCS-1: Contains cables, sockets, 1x 1-phase PDU, and tools.
  • PCS-3: Contains main power equipment, 1x 3-phase PDU (PDU-01), and cables.
  • UPS-01: Contains rack-mounted UPS for AV desk backup power.

Setup Steps

1. Main Power Connection
Schematics: Pages 1-4 Power Distribution Layout Plan, 6-6 Power Distribution Wiring Diagram, 6-10 PDU Circuit Breaker Schedule

  • A qualified electrician must connect PDU-01 to the venue distribution board.
  • Set up the PDU circuit breakers according to the schedule.
🗺️ View Associated Schematics (Pages 1-4, 6-6)6, 6-10)
1-4 Power Distribution Layout Plan showing PDU, UPS, and power distribution locations / 电源分配布局图,显示 PDU、UPS 及电源分配位置

6-6 Power Distribution Wiring Diagram showing PDU-01, power sockets, audio headend power, TVs, and LED wall power distribution / 电源分配接线图,显示 PDU-01、电源插座、音频主控供电、电视及 LED 屏幕电源分配

Note: Page 6-10 PDU Circuit Breaker Schedule is referenced in the full drawing set, but it is not currently included as an image on the master schematics page. Add it to the master page first if you want it embedded here.

6-10 PDU Circuit Breaker Schedule listing breaker loads for back row TVs, main video control desk, stage AV equipment, audio system, and LED walls / PDU 断路器清单,列出后排电视、主视频控制台、舞台影音设备、音频系统及 LED 屏幕的断路器负载

2. Pull Power Cables to AV Booth
Schematics: Pages 1-4 Power Distribution Layout Plan, 6-7 Power Distribution Video Control Desk Wiring Diagram

  • Pull power cables from the A/V booth to a wall socket.
  • Install the UPS (UPS-01) for the video control desk.
🗺️ View Associated Schematics (Pages 1-4, 6-7)
1-4 Power Distribution Layout Plan showing PDU, UPS, and power distribution locations / 电源分配布局图,显示 PDU、UPS 及电源分配位置

6-7 Power Distribution Video Control Desk Wiring Diagram showing UPS-01, VHEC-1, wireless receivers, intercom master unit, and video control desk power connections / 视频控制台电源接线图,显示 UPS-01、VHEC-1、无线接收器、对讲主机及视频控制台电源连接

3. Pull Power Cables to Stage
Schematics: Pages 1-4 Power Distribution Layout Plan, 6-6 Power Distribution Wiring Diagram

  • Pull power cables from behind the stage up onto the stage for the clock.
🗺️ View Stage PowerAssociated Schematics (Pages 1-4, 6-6)
1-4 Power Distribution Layout Plan showing PDU, UPS, and power distribution locations / 电源分配布局图,显示 PDU、UPS 及电源分配位置

6-6 Power Distribution Wiring Diagram showing PDU-01, power sockets, audio headend power, TVs, and LED wall power distribution / 电源分配接线图,显示 PDU-01、电源插座、音频主控供电、电视及 LED 屏幕电源分配

4. Assist with Cabling Protection

  • When done, help the Audio Cabling Team to cover cabling with carpet and floor channels.

Completion Checklist

  • Main PDU connected by qualified electrician
  • Circuit breakers set according to schedule
  • Power cables pulled to A/V booth and stage (clock)clock
  • Audio Cabling Team assisted with cable protection
  • Keyman inspection completed

Dismantling Procedure

  • Wait for the department briefing and prayer 30 minutes after the program ends on Sunday before dismantling.
  • Ensure all AV equipment is powered down before disconnecting power distribution equipment.
  • Gather all power cables, PDU, and UPS and bring to the designated area.
  • Note for team leader: Use the Bill of Materials (BOM) to cross off every box or case before it is brought to the truck:
    • PCS-1
    • PCS-3
    • UPS-01

🇨🇳 中文说明

目的
根据图纸为所有音视频设备和讲台分配电源,确保安全的走线和连接。

⚠️ 安全与安装提示
• 必须由合格的电工将配电单元 (PDU) 连接到讲台后方走廊的场地配电盘(三相电源)。
• 不要让电路过载。
• 确保行人免受绊倒和触电的危险。使用线缆盖板或将电线悬挂在高处。

参考资料

所需设备箱

  • PCS-1: 包含线缆、插座、1 个单相 PDU 和工具。
  • PCS-3: 包含主电源设备、1 个三相 PDU (PDU-01) 和线缆。
  • UPS-01: 包含机架式不间断电源 (UPS),用于音视频控制台的备用电源。

安装步骤

1. 主电源连接
图纸:1-4 电源分配布局图、6-6 电源分配接线图、6-10 PDU 断路器清单

  • 必须由合格的电工将 PDU-01 连接到场地配电盘。
  • 根据清单设置 PDU 断路器。
🗺️ 查看相关图纸(图纸 1-4, 6-6)6, 6-10)
1-4 Power Distribution Layout Plan showing PDU, UPS, and power distribution locations / 电源分配布局图,显示 PDU、UPS 及电源分配位置

6-6 Power Distribution Wiring Diagram showing PDU-01, power sockets, audio headend power, TVs, and LED wall power distribution / 电源分配接线图,显示 PDU-01、电源插座、音频主控供电、电视及 LED 屏幕电源分配

提示: 完整图纸中引用了 6-10 PDU 断路器清单,但目前主图纸页面没有包含该图片。如果要在这里嵌入,请先将 6-10 添加到主图纸页面。

6-10 PDU Circuit Breaker Schedule listing breaker loads for back row TVs, main video control desk, stage AV equipment, audio system, and LED walls / PDU 断路器清单,列出后排电视、主视频控制台、舞台影音设备、音频系统及 LED 屏幕的断路器负载

2. 铺设音视频控制台电源线
图纸:1-4 电源分配布局图、6-7 视频控制台电源接线图

  • 将电源线从音视频控制台拉到墙上的插座。
  • 安装用于视频控制台的不间断电源 (UPS-01)。
🗺️ 查看相关图纸(图纸 1-4, 6-7)
1-4 Power Distribution Layout Plan showing PDU, UPS, and power distribution locations / 电源分配布局图,显示 PDU、UPS 及电源分配位置

6-7 Power Distribution Video Control Desk Wiring Diagram showing UPS-01, VHEC-1, wireless receivers, intercom master unit, and video control desk power connections / 视频控制台电源接线图,显示 UPS-01、VHEC-1、无线接收器、对讲主机及视频控制台电源连接

3. 铺设讲台电源线
图纸:1-4 电源分配布局图、6-6 电源分配接线图

  • 将电源线从讲台后方拉到讲台上(供时钟使用)。将电源线从讲台后方拉到讲台上,供时钟使用。
🗺️ 查看讲台电源相关图纸(查看相关图纸(图纸 1-4, 6-6)
1-4 Power Distribution Layout Plan showing PDU, UPS, and power distribution locations / 电源分配布局图,显示 PDU、UPS 及电源分配位置

6-6 Power Distribution Wiring Diagram showing PDU-01, power sockets, audio headend power, TVs, and LED wall power distribution / 电源分配接线图,显示 PDU-01、电源插座、音频主控供电、电视及 LED 屏幕电源分配

4. 协助线缆保护

  • 自己的工作完成后,协助音频布线组使用地毯和地面线槽覆盖并保护线缆。

完成检查表

  • 合格的电工已连接主 PDU
  • 断路器已按清单设置
  • 电源线已拉至音视频控制台和讲台(时钟)电源线已拉至音视频控制台和讲台时钟
  • 已协助音频布线组进行线缆保护
  • 负责人已检查确认

拆卸步骤

  • 在星期日节目结束 30 分钟后,等待整个部门的简短会议和祷告后再开始拆除工作。
  • 在断开配电设备之前,确保所有音视频设备已关闭电源。
  • 收集所有电源线、PDU 和 UPS,并带到指定区域。
  • 组长注意: 在将每个箱子或设备箱搬上卡车前,请使用物料清单 (BOM) 核对并划掉每一项:
    • PCS-1
    • PCS-3
    • UPS-01