Video Cabling & TVs Setup / 视频布线及电视安装
🎬 Video Cabling & TVs Team / 视频布线及电视组
| Team / 小组 | Members / 成员 |
|---|---|
| Video Cabling & TVs / 视频布线及电视 | • Keiichi 加藤圭一 🔑 |
🇬🇧 English Instructions
Purpose
This section provides the specific setup and dismantling instructions for the Video Cabling & TVs Team. This team is responsible for setting up displays around the venue and routing SDI video cables to them.
Required References
- Full Drawing Set: 📎 Complete PDF
- Congregation Job Hazard Analysis (DC-85): 📁 Google Drive Folder
- Specific Schematics:
- 1-3 Video Equipment Layout Plan
- 1-5 Cable Pathway Plan
- 4-1 Stage Area Equipment Layout Large Scale View
- 6-5 Video Display Wiring Diagram
- 6-6 Power Distribution Wiring Diagram
- 6-9 Video and Power Equipment Schedule
- Event Content List: Cases VDS-1, VDS-2, VDS-3, VSC-01, VSC-02, CPS-1, CPS-3
Required Equipment Cases
- VDS-1: Contains 3x 43" Samsung TVs with table stands.
- VDS-2: Contains the stage confidence monitor, digital clock, SDI distributor, and SDI-HDMI converter.
- VDS-3: 2 sets, each containing a 65" TV with an electrical-lift wheel case.
- VSC-01: 2 sets, each containing 7x 25 m SDI cables.
- VSC-02: 2 sets, each containing 5x 50 m SDI cables.
- CPS-1: Contains 10x 3-channel floor cable protectors and 10x rubber mats.
- CPS-3: Contains carpet strips.
The schematics assign four 43" VDS-1 TVs: TV-3, TV-4, TV-5, and TV-7. The current BOM/Event Content List provides only 3x 43" TVs in VDS-1. Confirm the source and final assignment of the additional 43" TV before VDS-1 equipment is distributed between the Video Cabling & TVs Team and Video Booth Team.
Setup Steps
1. Install TVs and Monitors
Schematics: Pages 1-3 Video Equipment Layout Plan, 4-1 Stage Area Equipment Layout Large Scale View, 6-9 Video and Power Equipment Schedule
- Install the TVs and monitors first so the team can confirm the exact locations where SDI cables need to be pulled.
- Confirm each display location before running cables.
- Install TV-1 and TV-2 in the seating area.
- Install TV-3 in the Accounting Department.
- Install TV-4 and TV-5 at the Stage Department positions.
- Install TV-6 as the stage confidence monitor.
- TV-7 is installed at the Video Control Desk by the Video Booth Team.
- Confirm the final allocation of the 43" VDS-1 TVs before distributing them between the two teams.
🗺️ View Display Location Schematics (Pages 1-3, 4-1, 6-9)



2. Pull SDI Cables
Schematics: Pages 1-3 Video Equipment Layout Plan, 1-5 Cable Pathway Plan, 6-5 Video Display Wiring Diagram
- Pull and route SDI cables to the confirmed display locations according to the schematics.
- When passing through the front-middle seating section, follow the route of the audio multicore cable (AMC-1).
- Keep SDI cables neat and avoid crossing walkways unless necessary.
- Handle SDI cables carefully. Avoid sharp bends, kinks, and twisting.
- Consider attaching a tag to each SDI cable identifying its destination if time permits.
🗺️ View Cable Routing Schematics (Pages 1-3, 1-5, 6-5)



3. Install Cable Protection
Schematics: Page 1-5 Cable Pathway Plan
- Use rubber cable protectors where cables cross walkways.
- Use carpet covers for cables running through seating areas.
- Coordinate with the Audio Cabling Team so shared audio and video cable routes are protected neatly.
🗺️ View Cable Pathway Schematic (Page 1-5)

4. Secure Cabling
- Wait until both the Audio Cabling Team and Video Cabling & TVs Team have finished pulling cables before fully securing shared cable routes.
- Secure cables neatly using the appropriate tape, carpet covers, rubber mats, or cable protectors.
- When using carpet covers in seating areas, secure one side first. Secure the other side after the entire installation is finished.
- Recheck all cable routes for trip hazards before completing the installation.
5. Connect Power and Verify Displays
Schematics: Pages 6-5 Video Display Wiring Diagram, 6-6 Power Distribution Wiring Diagram
- Coordinate with the Power Distribution Team before connecting or powering on displays.
- Connect the required display power after the Power Distribution Team confirms that power is ready.
- Coordinate with the Video Booth Team to confirm that the correct video signal reaches each display.
- Confirm that all installed displays operate correctly and show a stable picture.
🗺️ View Display Wiring and Power Schematics (Pages 6-5, 6-6)


Completion Checklist
- Final allocation of the 43" VDS-1 TVs confirmed
- TV-1 and TV-2 installed in the seating area
- TV-3 placed in the Accounting Department
- TV-4 and TV-5 installed at the Stage Department positions
- TV-6 confidence monitor installed
- TV-7 allocation coordinated with the Video Booth Team
- SDI cables pulled to confirmed display locations
- SDI route follows the audio multicore cable (AMC-1) through the front-middle seating section
- Walkway cables protected with rubber cable protectors
- Seating-area cables protected with carpet covers
- Cabling secured after both audio and video cabling are completed
- Display power connected after confirmation from the Power Distribution Team
- Video signal verified at all installed displays with the Video Booth Team
- Keyman inspection completed
Dismantling Procedure
- Wait for the department briefing and prayer 30 minutes after the program ends on Sunday before dismantling.
- Carefully power down the displays.
- Disconnect all SDI and power cables from the displays.
- Remove cable protectors, rubber mats, and carpet covers carefully.
- Coil SDI cables carefully, allowing each cable to follow its natural shape. Avoid sharp bends, kinks, and twisting.
- Label cables as needed before packing.
- Gather all displays, cables, and cable-protection materials and bring them to the designated area.
- Note for team leader: Use the Bill of Materials (BOM) to cross off every box or case before it is brought to the truck:
- VDS-1
- VDS-2
- VDS-3 ×2
- VSC-01 ×2
- VSC-02 ×2
- CPS-1
- CPS-3
🇨🇳 中文说明
目的
本页面提供 视频布线及电视组 的具体安装和拆卸说明。该小组负责在场馆各处安装显示屏幕,并将 SDI 视频线布置连接到这些屏幕。
参考资料
- 完整图纸: 📎 完整 PDF 文件
- 《会众工作危险性分析》(DC-85): 📁 Google Drive 文件夹
- 相关图纸:
- 1-3 视频设备布局图
- 1-5 电缆路径图
- 4-1 舞台区域设备布局大比例图
- 6-5 视频显示系统接线图
- 6-6 电源分配接线图
- 6-9 视频和电源设备清单
- 大会设备清单: 设备箱 VDS-1、VDS-2、VDS-3、VSC-01、VSC-02、CPS-1、CPS-3
所需设备箱
- VDS-1: 包含 3 台 43 英寸三星电视及桌面支架。
- VDS-2: 包含讲台提示屏幕、数字时钟、SDI 分配器及 SDI-HDMI 转换器。
- VDS-3: 共 2 套,每套包含 1 台 65 英寸电视及带电动升降装置的轮式设备箱。
- VSC-01: 共 2 套,每套包含 7 条 25 米 SDI 视频线。
- VSC-02: 共 2 套,每套包含 5 条 50 米 SDI 视频线。
- CPS-1: 包含 10 个三槽地面电缆盖板和 10 块橡胶垫。
- CPS-3: 包含地毯盖板。
图纸将 4 台 43 英寸 VDS-1 电视分别指定为 TV-3、TV-4、TV-5 和 TV-7,但目前的 BOM/大会设备清单中,VDS-1 只有 3 台 43 英寸电视。在视频布线及电视组和视频控制台组分配 VDS-1 设备前,请先确认额外一台 43 英寸电视的来源和最终委派位置。
安装步骤
1. 安装电视和屏幕
图纸:1-3 视频设备布局图、4-1 舞台区域设备布局大比例图、6-9 视频和电源设备清单
- 首先安装电视和屏幕,以便确认 SDI 视频线需要拉到的确切位置。
- 拉线前确认每台显示设备的位置。
- 在座位区域安装 TV-1 和 TV-2。
- 将 TV-3 安装在会计部。
- 将 TV-4 和 TV-5 安装在讲台部门的指定位置。
- 将 TV-6 安装为讲台提示屏幕。
- TV-7 由视频控制台组安装在视频控制台。
- 在两个小组分配 43 英寸 VDS-1 电视前,先确认最终的电视分配安排。
🗺️ 查看显示设备位置图纸(图纸 1-3, 4-1, 6-9)



2. 布置 SDI 视频线
图纸:1-3 视频设备布局图、1-5 电缆路径图、6-5 视频显示系统接线图
- 根据图纸,将 SDI 视频线拉到已经确认好的显示设备位置。
- 穿过前方中间座位区时,请沿着音频多芯线缆(AMC-1)的路线铺设 SDI 视频线。
- 保持 SDI 视频线整齐,尽量避免穿过过道。
- 小心处理 SDI 视频线,避免急弯、打结和扭转。
- 如果时间允许,请考虑为每根 SDI 视频线贴上标签,标明连接位置。
🗺️ 查看线缆路线图纸(图纸 1-3, 1-5, 6-5)



3. 安装线缆保护盖板
图纸:1-5 电缆路径图
- 在线缆穿过过道的位置使用橡胶电缆盖板。
- 座位区域内的线缆使用地毯盖板。
- 与音频布线组协调,确保共用的音频和视频线缆路线整齐并受到保护。
🗺️ 查看电缆路径图(图纸 1-5)

4. 固定线缆
- 等音频布线组和视频布线及电视组都完成拉线后,再完全固定共用的线缆路线。
- 使用适当的胶带、地毯盖板、橡胶垫或电缆盖板整齐固定线缆。
- 在座位区域使用地毯盖板时,先固定一侧。等整个安装完成后再固定另一侧。
- 完成安装前,再次检查所有线缆路线是否存在绊倒危险。
5. 连接电源并确认显示设备
图纸:6-5 视频显示系统接线图、6-6 电源分配接线图
- 连接或开启显示设备前,先与电源分配组协调。
- 电源分配组确认电源准备好后,再连接显示设备所需的电源。
- 与视频控制台组协调,确认每台显示设备都收到正确的视频信号。
- 确认所有已安装的显示设备工作正常,并显示稳定的画面。
🗺️ 查看显示系统接线和电源图纸(图纸 6-5, 6-6)


完成检查表
- 已确认 43 英寸 VDS-1 电视的最终分配安排
- TV-1 和 TV-2 已安装在座位区域
- TV-3 已放置在会计部
- TV-4 和 TV-5 已安装在讲台部门的指定位置
- TV-6 讲台提示屏幕已安装
- 已与视频控制台组协调 TV-7 的分配
- SDI 视频线已拉到确认好的显示设备位置
- 前方中间座位区的 SDI 视频线已沿音频多芯线缆(AMC-1)的路线铺设
- 过道线缆已使用橡胶电缆盖板保护
- 座位区域线缆已使用地毯盖板保护
- 音频和视频布线完成后,线缆已固定
- 经电源分配组确认后,显示设备电源已连接
- 已与视频控制台组确认所有已安装显示设备的视频信号
- 负责人已检查确认
拆卸步骤
- 在星期日节目结束 30 分钟后,等待整个部门的简短会议和祷告后再开始拆除工作。
- 小心关闭显示设备电源。
- 从显示设备上断开所有 SDI 视频线和电源线。
- 小心移除电缆盖板、橡胶垫和地毯盖板。
- 小心盘绕 SDI 视频线,让线缆顺着自然方向盘绕,避免急弯、打结和扭转。
- 装箱前按需要标识线缆。
- 收集所有显示设备、线缆和线缆保护材料,并带到指定区域。
- 组长注意: 在将每个箱子或设备箱搬上卡车前,请使用物料清单 (BOM) 核对并划掉每一项:
- VDS-1
- VDS-2
- VDS-3 ×2
- VSC-01 ×2
- VSC-02 ×2
- CPS-1
- CPS-3