Audio Cabling Setup
Audio Cabling Team / 音频布线组
Item / 项目 |
|
|---|---|
Keyman | *To be assigned / |
# | Name / 姓名 |
|---|---|
1 | |
2 | |
3 | |
4 | |
5 | |
6 |
Purpose / 目的
Install, protect, and label all audio cabling according to the Schematics before system commissioning.
根据图纸安装、保护并标识所有音频线缆,为系统调试做好准备。
Required References / 参考资料
- Schematics / 图纸
Safety Notes / 安全提醒
- Keep walkways clear. / 保持通道畅通。
- Protect all cables crossing walkways. / 所有经过通道的线缆都必须加以保护。
- Confirm routing before securing cables. / 固定线缆前确认走线路径。
Setup Steps / 安装步骤
1. Install Snake Cable / 铺设主音频蛇线
Schematics / 图纸
- Page 1-5
English**English**
- Pull the snake cable according to the Schematics.
- Start at the front stage-left position, between [2] and [3].
- Verify routing before securing the cable.
中文
- 按照图纸铺设主音频蛇线。
- 从讲台前区左侧的位置开始,位于 [2] 和 [3] 之间。
- 固定线缆前确认走线路径正确。
2. Install Speaker Cables / 铺设扬声器线缆
Schematics / 图纸
- Pages 1-2, 1-5, 4-1
English**English**
- Pull all speaker cables according to the Schematics.
- Connect each loudspeaker group.
- Verify cable labels before connection.
中文
- 按照图纸铺设所有扬声器线缆。
- 连接各扬声器组。
- 连接前确认线缆标签正确。
3. Protect Cabling / 保护线缆
Schematics / 图纸
- Pages 1-5, 4-1
English**English**
- Use tape, carpet covers, or floor cable channels (rubber covers) where required.
- Ensure all walkways remain safe. Use cable channels when crossing a walkway.
中文
- 根据需要使用胶带、地毯压线盖或地面线槽(橡胶过线槽)固定和保护线缆。
- 确保所有通道保持安全畅通。线缆穿越通道时,必须使用线槽(过线槽)进行保护。
Completion Checklist / 完成检查表
- Snake cable installed / 主蛇线已铺设
- Speaker cables installed / 扬声器线缆已铺设
- Routing matches Schematics / 走线符合图纸
- Cables protected / 线缆已保护
- Walkways safe / 通道安全
- Keyman inspection completed / 负责人已检查确认
Dismantling / 拆卸
Procedure / 步骤
English
- Gather all audio cabling.
- Remove carpet covers and floor channels.
- Bring all equipment to the designated collection area.
- Confirm no cables remain in the seating area.
中文
- 收集所有音频线缆。
- 移除地毯覆盖物和线槽。
- 将所有设备带到指定集合区域。
- 确认座位区域没有遗留线缆。